2017 Updates
Completed in 2017
Mattresses, sheets, blankets, uniforms, clothing and shoes again for another year.
Fencing: 51 panels built now.
Girls dorm: Plumbing issues.
Boys Dorm: Plumbing issues, parged the walls inside and painted, outdoor skirt, stairs.
Outdoor Kitchen: Built sheltered kitchen for cooking and wired.
Kitchen and community area: finished the floor with a smooth finish coat on the floor, parged the walls, wired for electricity, out door parging, doors and stairs.
Pump House: piping, new pump due to high useage, water useage alarm.
Duplex: Board on the ceiling on one side and a dividing wall built for privacy to the roof.
Communal Kitchen – still needs windows, kitchen cabinents and counters.
Duplex – still needs blinds, kitchens and one sided boarded on the ceiling
Water storage buildings
Pump House floors cemented, doors placed and locks
Fencing: 313 panels needed still. 51 built YEAH !!!!!
Mattresses, sheets, blankets, uniforms, clothing and shoes again for another year.